Transportation of Converter

Project Description

Super Freight’s scope of work included transport & barging of two nos S-50 Redial Flow Ammonia Converter + 11 Packages from L&T Hazira to Mandwa Jetty and door delivery to RCF, Thal. A special bypass bridge was constructed to transport the equipment from Mandwa Jetty to Site.

Project Details

Step 1

Ammonia Converter Arrives Hazira Jetty.

Step 2

Loading onto Barge & Securing the cargo on specially fabricated stools.

Step 3

Cargo in transit.

Step 4

Construction of Bypass road at Mandwa.

Step 5

Temporary ramp set up at destination, after barge arrives.

Step 6

Converter successfully discharged for onward delivery.